Facts and Figures

  • Location:  Southeast of the intersection of Trissino Dr. and Escarpment Blvd.
  • Estimated Cost of Proposed Projects: $36,277,000
  • Project Type: New School Construction
  • Anticipated Opening Date: August 2020
  • Planned Capacity: 552
  • 2016/2017 Utilization: NA

Stay Informed

Drone Footage

Overview

The New Southwest Elementary School will provide relief to the over-utilized Kiker and Baranoff Elementary Schools with a planned capacity of 522 students. This facility is one of the first schools to be designed and built in the 2017 Bond Program. Following the AISD vision of creating 21st-century learning spaces for students, the new elementary school will incorporate flexible spaces allowing for collaborative, interdisciplinary, and project-driven learning..

Scope of Work 2017 Bond

  • New School Construction

Published: Data is from the September 10, 2019, CBOC report. More information can be found here on the CBOC page.


Project Status

  • Construction PhaseConstruction Phase

    New Build

    Piers complete. Site utilities, underground electrical and plumbing ongoing. Grade beams for building 2 and with slab placement planned for beginning of September. - 2017 Bond

    Status: On Schedule Percent Complete: 11%
    Expected Completion: July 2020

  • Construction Documents PhaseConstruction Documents Phase

    New Build

    Design and construction of a new state-of-the-art facility with increased capacity. Technology improvements. - 2017 Bond

    Status: On Schedule Percent Complete: 11%
    Expected Completion: July 2020

Contracts are subject to be rebid; timeline depends on board approval.

Multi Campus Project Status

Bond Financials

School/Facility (per 2017 Bond Book) Bond Book Project Budget* Current Amount Committed Expended**
Calculation A B C D F =B-C-D
New Northeast MS $36,227,000 $31,625,670 $3,250,834 $28,846,606 ($471,770)

Note: Contingency funds to be prioritized for overcrowding relief for the Northwest, Blazier, Cowan and Baranoff communities.

*Difference between 2017 Bond Book Amount and Project Budget is reserved for work in later phases, program-wide bond services, technology, administration and contingency.

** Commitments are unpaid expense obligations such as requisitions and purchase orders.

Legend
  • Bond Book – Voter approved amount including administrative overhead.
  • Project Budget – Amount approved.
  • Current Budget – Amount approved.
  • Committed – Contracts approved.
  • Expended – Amount actually spent.

2017 Bond Districtwide Financials

Proposed Construction Schedule

 

Previous Bond Program Projects

  • 2017

    2017 Bond Book
  • 2013

    2013 Bond Book
  • 2008

    2008 Bond Book
  • 2004

    2004 Bond Book
 