Facts and Figures

  • Location: 7105 Berkman Dr.
    Austin, TX 78704
  • Estimated Cost of Proposed Projects: $151,000 
  • Year Built: 1963
  • Building Area: 59,005 Sq. Ft.
  • Site: 20 Acres

Stay Informed

Overview

Nelson Field is located near Reagan Early College High School. The multiuse facility serves as home stadium for LBJ Early College High School, Anderson High School, Eastside Memorial High School and Reagan Early College High School. The stadium, built in 1963, has a capacity of 8,800 spectators.

Scope of Work 2017 Bond

  • Districtwide Fire and Intrusion Alarm Upgrades
  • Districtwide Security Camera Replacements 
  • Technology: Network System Improvements 

Published: Data is from the June 9, 2020, CBOC report. More information can be found here on the CBOC page.


Project Status

  • Financial Closeout PhaseFinancial Closeout Phase

    Accessibility Renovations at Nelson Field, Anderson, Lanier, Clifton Center, & CAC

    Phase 1: Nelson Baseball Field: Provide accessible seating at baseball field. Phase 2: Address TAS-identified deficiencies at CTE-related areas for 3 facilities (Anderson HS, Lanier HS, Clifton Center)

    Percent Complete: 20%

  • Complete PhaseComplete Phase

    Renovations at Nelson Field

    Renovations to repair and resurface parking lots, replacement of select exhaust fans, hard ceilings, domestic water boilers, HVAC pumps, exterior door assemblies, interior lighting, sectional doors, plumbing faucets, fixtures, lavatories and domestic water lines.

    Percent Complete: 100%

  • Complete PhaseComplete Phase

    Repair/Replace Turf at Nelson Field

    Replace artificial turf (carpet)

    Percent Complete: 100%

Contracts are subject to be rebid; timeline depends on board approval.

Multi Campus Project Status

Bond Financials

School/Facility (per 2017 Bond Book) Bond Book Project Budget* Actuals Commitments Project Balance**
Calculation A B C D F =B-C-D
Nelson Field /Bus Terminal-Critical Facility Deficiencies $468,000 $623,170 $498,502 $114,330 $10,339
Legend
  • Bond Book – Voter approved amount including administrative overhead.
  • Project Budget – Amount approved.
  • Current Budget – Amount approved.
  • Committed – Contracts approved.
  • Expended – Amount actually spent.

2017 Bond Districtwide Financials

Previous Bond Program Projects

  • 2017

    2017 Bond Book
  • 2013

    2013 Bond Book
  • 2008

    2008 Bond Book
  • 2004

    2004 Bond Book
 