Facts and Figures
- Location: 4601 Pecan Brook Dr.
Austin, TX 78724 - Estimated Cost of Proposed Projects: $570,000
- Year Built: 2003
- Building Area: 60,294 Sq. Ft.
- Site: 44 Acres
Facility Condition Assessment
This Facility | 45 |
---|---|
District Average | 62 |
FCA Legend
- Excellent: 90-100
- Good: 70-89
- Average: 50-69
- Poor:30-49
- Fail: ≺ 30
Stay Informed
Overview
Named for Dr. Exalton and Wilhelmina Delco, the Delco Activity Center is located in northeast Austin, near LBJ Early College High School. It opened in fall 2002 and provides facilities for competition in basketball, wrestling, volleyball, cheer-leading and dance as well as student musical performances.
Scope of Work 2017 Bond
- Districtwide Fire and Intrusion Alarm Upgrades
- Districtwide Security Camera Replacements
- Site Drainage Improvements
-
Technology: Network System Improvements
Published: Data is from the January 26, 2021, CBOC report. More information can be found here on the CBOC page.
Project Status
-
Construction Phase
Critical Repairs - Crawl Space
Address water infiltration coming in at corner entry hollow metal storefront systems; install canopies at two entries; repair uneven grade between building slab and adjacent flatwork; replace unsafe concrete panel screening face with chain link fence.
Status: On Schedule Percent Complete: 5%
Expected Completion: 6/30/21
Notes: Coordination with AISD Athletics is ongoing. Permit was paid for and construction will start soon. Coordination with facility events and safety needs will be addressed in upcoming Pre-Construction meeting. -
Complete Phase
2013 Bond Contingency Approved
Repair Detention Ponds at Overton, Garcia and Delco
-
Complete Phase
Renovations at Delco Activity Center
Repair selected parking lot pavement areas and perimeter sidewalks; upgrade fire and intrusion alarm systems; HVAC renovations.
Percent Complete: 100%
-
Complete Phase
Renovations at Delco Activity Center
Address drainage deficiencies and modifications to storm drain system, including modifications to flatwork at building entries
Percent Complete: 100%
Contracts are subject to be rebid; timeline depends on board approval.
Multi Campus Project Status
Bond Financials
School/Facility (per 2017 Bond Book) | Bond Book | Project Budget* | Actuals | Commitments | Project Balance** |
---|---|---|---|---|---|
Calculation | A | B | C | D | F =B-C-D |
Delco Activity Center-Critical Facility Deficiencies | $417,000 | $554,307 | $36,481 | $489,394 | $28,432 |
Legend
- Bond Book – Voter approved amount including administrative overhead.
- Project Budget – Amount approved.
- Current Budget – Amount approved.
- Committed – Contracts approved.
- Expended – Amount actually spent.