Facts and Figures

  • Location: 3701 Woodbury Dr.
    Austin, TX 78704
  • Estimated Cost of Proposed Projects: $1,721,000
  • Year Built: 1983
  • Building Area: 116,305 Sq. Ft.
  • Site: 19 Acres

Stay Informed

Overview

The primary function of the Central Warehouse is that of a holding facility for goods, materials, furniture, dry food products and equipment for subsequent distribution to school campuses and other AISD facilities. In addition to dry goods and materials, the Central Warehouse stores refrigerated and frozen food products for distribution to school kitchens.

Scope of Work 2017 Bond

  • Districtwide Fire and Intrusion Alarm Upgrades
  • Districtwide Security Camera Replacements 
  • Electrical System Improvements

Project Status

  • ConsructionConstruction

    173260-GROUP: Urgent Roofing/Waterproofing Repairs at Various AISD Campuses

    Work is ongoing as needed at various campuses.
    Complete: 80% Expect Completion: 1/15/20
  • Completed ProjectCloseout Phase

    Move Food Service to the Central Warehouse

    Amendment No.1 to 170035-ADMIN: Phase 1 Design and Construction to move Food Service from Baker to the Central Warehouse.
  • Completed ProjectComplete Phase

    Cold Storage Addition at Central Warehouse

    Construction of cold/frozen food storage addition; electrical upgrades; HVAC replacement, and roof repairs at the dry storage warehouse.

Contracts are subject to be rebid; timeline depends on board approval.

Multi Campus Project Status

Bond Financials

School/Facility (per 2017 Bond Book) Bond Book Project Budget* Current Amount Committed Expended**
Calculation A B C D F =B-C-D
Central Warehouse $295,000 $126,340 - - $126,340

Note: Contingency funds to be prioritized for overcrowding relief for the Northwest, Blazier, Cowan and Baranoff communities.

*Difference between 2017 Bond Book Amount and Project Budget is reserved for work in later phases, program-wide bond services, technology, administration and contingency.

** Commitments are unpaid expense obligations such as requisitions and purchase orders.

Legend
  • Bond Book – Voter approved amount including administrative overhead.
  • Project Budget – Amount approved.
  • Current Budget – Amount approved.
  • Committed – Contracts approved.
  • Expended – Amount actually spent.

2017 Bond Districtwide Financials


Published: Data is from the August 13, 2019, CBOC report. More information can be found here on the CBOC page.

Previous Bond Program Projects

  • 2017

    2017 Bond Book
  • 2013

    2013 Bond Book
  • 2008

    2008 Bond Book
  • 2004

    2004 Bond Book
 

Questions or Comments

Your feedback is welcome!

Contact us by phone or contact below.

Bond Hotline: 512-414-9595

Facility Maintenance Help Desk: 512-414-2199