Facts and Figures

  • Location: 3200 Jones Rd.
    Austin, TX 78745
  • Estimated Cost of Proposed Projects: $1,721,000
  • Year Built: 1977
  • Building Area: 180,614 Sq. Ft.
  • Site: 48 Acres

Stay Informed

Overview

The Toney Burger Activity Center is an athletics facility and event venue, which hosts football, basketball, baseball, soccer, marching band and track activities. It also houses the headquarters for AISD’s Athletics Department. Constructed in 1977, the Toney Burger Activity Center sits on 48.1 acres in South Austin.

Scope of Work 2017 Bond

  • Districtwide Fire and Intrusion Alarm Upgrades
  • Districtwide Security Camera Replacements 
  • Electrical System Improvements
  • Full Track Replacement 

  • Lighting and Security Improvements 

  • Sidewalk and Pavement Improvements 

  • Structural Repairs 

  • Technology: Network System Improvements 


Published: Data is from the January 26, 2021, CBOC report. More information can be found here on the CBOC page.


Project Status

  • Construction PhaseConstruction Phase

    Critical Repairs - Electrical,Lighting,Pavement,Playfields,Structural

    • Electrical System Improvements • Full Track Replacement • Lighting and Security Improvements • Sidewalk and Pavement Improvements • Structural Repairs

    Status: On Schedule Percent Complete: 10%
    Expected Completion: 8/7/21
    Notes: Contract is executed for phase 1 CSP delivery involving lights and gates. Phase 2 will be a JOC delivery for the track replacement and will go out for solicitation in January 2021.

  • Construction PhaseConstruction Phase

    2013 Bond Contingency Approved

    Burger Stadium Repairs

  • Financial Closeout PhaseFinancial Closeout Phase

    Mechanical Work at Burger Athletic Complex

    Installation of additional chiller capacity and additional air handling units; replacement of HVAC cold and hot water circulation piping,circulation pumps,boiler,motor controllers,air handlers and controls.

    Percent Complete: 20%

  • Complete PhaseComplete Phase

    2013 Bond Contingency Approved

    Repair of Running Tracks at Burger Center,Austin HS,Lively MS,Lamar MS

  • Complete PhaseComplete Phase

    Replace Paving at Burger Activity Center

    Repair and re-surface selected asphalt paving area - NE corner

    Percent Complete: 100%

  • Complete PhaseComplete Phase

    Renovations at Burger Athletic Complex

    Concession & Restroom/ Locker room renovations. Security updates / Stadium RR ADA / finish upgrades,misc. finishes and lighting upgrades,CCTV @ stadium

    Percent Complete: 100%

  • Complete PhaseComplete Phase

    Replace Paving at Saegert Bus Terminal and Burger Center

    Repair and re-surface selected asphalt paving areas,including all paving work at Saegert Bus Terminal and all work at Burger Athletic Center except for northeast parking lot. Northeast parking lot at Burger was project 140053-BURGR,which is complete.

    Percent Complete: 100%

Multi Campus Project Status

Bond Financials

School/Facility (per 2017 Bond Book) Bond Book Project Budget* Actuals Commitments Project Balance**
Calculation A B C D F =B-C-D
Burger Athletic Complex-Critical Facility Deficiencies $1,265,000 $1,094,533 $73,892 $261,834 $758,807
Legend
  • Bond Book – Voter approved amount including administrative overhead.
  • Project Budget – Amount approved.
  • Current Budget – Amount approved.
  • Committed – Contracts approved.
  • Expended – Amount actually spent.

2017 Bond Districtwide Financials

Previous Bond Program Projects

  • 2017

    2017 Bond Book
  • 2013

    2013 Bond Book
  • 2008

    2008 Bond Book
  • 2004

    2004 Bond Book
 

Questions or Comments

Your feedback is welcome!

Contact us by phone or contact below.

Phone: 512-414-9595

Contact CBOC