2004 Bond Program Scope of Work
• Install additional exterior security lighting
• Install cast iron protective boots at downspouts
• Remove door at auditorium stage
• Repair/replace approximately 21,500 square feet of built-up roofing
• Replace selected ventilation system equipment
• Replace grease trap serving kitchen
• Replace main sanitary sewer line
• Replace sanitary sewer and and water lines serving kitchen
• Install playslab cover
• Install safety and security enhancements
2008 Bond Program Scope of Work
• Technology upgrades
• Cafeteria and kitchen improvements
Phases
| Current |
Schedule |
Budget |
General |
Environmental |
| Install additional exterior security lighting; replace grease trap; replace deteriorated sanitary sewer lines between building and street; replace deteriorated sanitary sewer and domestic water lines under kitchen; install cast iron protective boots at downspouts; remove deteriorated door and infill with masonry at stage loft; remove abandoned heating, ventilation and air conditioning equipment; install heating, ventilation and air conditioning unit for room 33. |
Complete. |
Over budget.* |
Paired with Allan Elementary School project. |
|
| Repair/replace approximately 21,500 square feet in built-up roofing. |
Complete. |
Within budget.* |
|
New replacement roof systems will provide increased thermal efficiency and solar reflectivity. |
| Drainage, ventilation and accessibility improvements. |
Complete. |
Under budget. Funded with 2002 Bond Program funds.* |
Grouped with seven other facilities. |
Environmental considerations are limited to on-site drainage projects. Care was taken to avoid excess soil erosion during construction. |
| Safety and security: card reader door access, door repair. |
Complete. |
Within budget.* |
Grouped with three other schools. |
|
| Safety and security: closed circuit TV. |
Complete. |
Within budget.* |
Grouped with four other schools. |
|
|
*Budget for the 2004 and 2008 Bond Programs are reported as both individual project budgets and overall
program budget. While specific projects may be over or under budget, the 2004 and 2008 Bond Programs remain well
within the total program budget.
Photos
Click on photo for larger version.
| There are no images for this project. |
|
|
Find Out What's Happening at your School
Recent News
No news available.
Upcoming Events
There are no events scheduled.
Other Events
|
For Contractors |
|
|