2004 Bond Program Scope of Work
• Construct eight-classroom addition with commons
• Connect roof downspouts to storm sewer system
• Improve storm/site drainage in selected areas
• Replace deteriorated expansion joints in exterior walls and repair masonry
• Replace ventilation system equipment for the administration area, cafeteria and gym
• Replace electrical conduit under kitchen
• Repair/replace sink hardware at classrooms
• Replace sanitary sewer lines serving kitchen
• Install playslab cover
• Install safety and security enhancements
• Replace heating, cooling and ventilation system equipment at kitchen and install new digital controls
2008 Bond Program Scope of Work
• Technology upgrades
• Replace heating, ventilation and air conditioning system equipment in kitchen and install new digital controls
Phases
| Current |
Schedule |
Budget |
General |
Environmental |
| Improve storm/site drainage in selected areas. |
Complete. |
Under budget. Funded with 2002 bond funds.* |
After field investigations, it was determined that proper drainage improvements should offset any ventilation requirements to control moisture in crawlspaces. |
Environmental considerations are limited to on-site drainage projects. Care was taken to avoid excess soil erosion during construction. |
| Modifications for better ventilation control and space utilization in main distribution frame (MDF) room. |
Complete. |
Under budget.* |
To improve temperature conditions in technology control room. |
|
| Kitchen hood fire suppression replacement. |
Complete. |
Under budget.* |
|
|
| Eight-classroom addition with commons and renovations, site drainage modifications, playslab cover and ventilation modifications and safety and security enhancements. |
Complete. |
Over budget.* |
|
New construction will meet Austin Energy two-star Green Building rating. |
| Construct fire lanes and additional parking. |
Complete. |
Under budget.* |
Sitework associated with classroom addition. |
|
| Install playslab cover. |
Complete. |
|
Grouped with five other schools. |
|
|
*Budget for the 2004 and 2008 Bond Programs are reported as both individual project budgets and overall
program budget. While specific projects may be over or under budget, the 2004 and 2008 Bond Programs remain well
within the total program budget.
Photos
Click on photo for larger version.
| There are no images for this project. |
|
|